03/16/2006
Consideration of Parks Waiver Request
Comm Summary
08:08 AM
08:55 AM
Final
Bill Summary
Final
FINAL VOTE - Approve the Parks request for a waiver from the six-month encumbrance rule in the amount of $1,410,000 ($1,300,000 CF and $110,000 FF) for the Off-Highway Vehicle project. The motion passed on a 5-0-1 vote.
Final
Follow-Up Discussion Regarding Capital Projects
Comm Summary
08:08 AM
08:55 AM
Final
Bill Summary
Final
Overview of Legislation Affecting the CDC
Comm Summary
08:08 AM
08:55 AM
Final
Bill Summary
Final
Update on Use of GOCO Funds for Parks and Wildlife
Comm Summary
08:08 AM
08:55 AM
Final
Bill Summary
Final
03/14/2006
Discussion of Potential Legislation
Comm Summary
08:07 AM
08:55 AM
Final
Bill Summary
Final
Introduce a committee bill to fund COP projects before the Senate Bill 97-1 diversion (Attachment A). The motion passed on a 5-1 vote.
Final
Change the date of the first transfer in the draft bill to reinstate an annual General Fund transfer (Attachment B) from July 1, 2006, to July 1, 2007. The motion failed on a vote of 2-4.
Final
Introduce a committee bill, to reinstate an annual $100 million General Fund transfer to the Capital Construction Fund (Attachment B). The motion passed on a vote of 6-0.
Final
Introduce a committee bill requiring the DOC to notify the CDC when the DOC issues requests for proposals to construct new private prisons (Attachment D). The motion passed on a vote of 4-2.
Final
03/09/2006
FY 2006-07 Capital Construction Prioritization
Comm Summary
07:38 AM
01:30 PM
Final
Bill Summary
Final
Moved to place the Department of Corrections Trinidad Correctional Facility Water Utilities project as 27a and Department of Corrections Colorado Territorial Correctional Facility Sanitary Sewer/Storm Distribution Improvements project as 27b on the Senator McElhany priority list (Attachment B). The motion passed on a 6-0 vote.
Final
Moved the Senator McElhany priority list (Attachment B) and further moved to place the design phase of the Department of Corrections' 1555 Sherman Street project as priority number 29a on Attachment B. The motion passed on a 6-0 vote.
Final
Moved to place the Colorado State University Diagnostic Medicine Center as priority number 10a on the Senator McElhany priority list (Attachment B). The motion passed on a 6-0 vote.
Final
Moved to place the Judicial Space Needs Assessment project as priority number 10b on the Senator McElhany priority list (Attachment B). The motion passed on a 5-1 vote.
Final