Date: 06/16/2010

Final
Department of Corrections State-Funded Supplemental Request

COMMITTEE ON CAPITAL DEVELOPMENT

Votes: View--> Action Taken:
Approve the state-funded supplemental request for PASS



09:05 AM -- Department of Corrections State-Funded Supplemental Request

The committee was called to order. A quorum was present. Ms. Deb Kugler, Budget Manager, and Mr. Richard Weems, Director of Facility Management Services, both of the Department of Corrections, presented a state-funded supplemental request for the Colorado State Penitentiary II, High-Custody Expansion (COP Project). Committee members received a summary of the request, prepared by Legislative Council Staff (Attachment A). Ms. Kugler gave background about the payment schedule for the certificates of participation (COP) for the project, including a supplemental request to eliminate the FY 2009-10 payment considered by the committee in February 2010. Ms. Kugler addressed questions about the project.
100616AttachA.pdf
BILL:Department of Corrections
TIME: 09:10:52 AM
MOVED:Riesberg
MOTION:Approve the state-funded supplemental request for the Colorado State Penitentiary II, High-Custody Expansion (COP Project) FY 2009-10 certificates of participation annual payment ($2,855,175 CCF). The motion carried on a vote of 6-0.
SECONDED:
VOTE
Renfroe
Yes
Schwartz
Yes
Sonnenberg
Yes
Vigil
Yes
Riesberg
Yes
Bacon
Yes
Final YES: 6 NO: 0 EXC: 0 ABS: 0 FINAL ACTION: PASS